All planned maintenance at the gas storage Inzenham-West is published here:Period | Description | Note |
---|
15.4.2024-19.4.2024 | XOV 0705 replacement. No Injection or Withdrawal possible during the maintenance | 5 days |
---|
8.10.2024 - 8.10.2024 08:00-16:00 | Safety System Test. No Injection or Withdrawal possible during the maintenance | 8 hours |
---|
9.10.2024 - 9.10.2024 08:00-16:00 | Safety System Test. No Injection or Withdrawal possible during the maintenance | 8 hours |
---|
19.8.2024 - 15.11.2024 06:00 - 16:00 | Maintenance of compressor No redundancy available, in case of technical issue/unplanned maintenance possible reduction of withdrawal/injection rate | 89 days 10 hours |
---|
To further minimize restrictions for shippers and storage customers, Storage System Operator (SSO) and Transmission System Operator (TSO) will use the Operational Balancing Account (OBA).
The aim is to have maintenances in the storage and in the connected network in parallel to minimize restrictions. Any restrictions from planned maintenance refer to the complete plant capacities. Individual contract parties will be informed bilaterally regarding their contract restrictions.NAFTA Speicher Inzenham will inspect and consider justified requests for shifting of maintenance.